Design Point Consultant Pvt. Ltd. Vs. The Union of India (Gujarat High Court)

Court: High Court of Gujarat
Head Notes:

On account of financial hardship, after the period of 1.5 years from the due date to make payment under Sabka Vishwas (Legacy Dispute Resolution) Scheme, 2019 [SVLDR Scheme], the Hon’ble Court allowed the petitioner to make payment of outstanding dues under the SVLDR Scheme. Further, in absence of issuance of pre-consultation notice, the Hon’ble Court quashed the Show Cause Notice.

Law:
Section(s): Sabka Vishwas (Legacy Dispute Resolution) Scheme, 2019
Counsel(s): Darshan B. Gandhi
Dowload Pdf File Click here to download the file in pdf format
Uploaded By Darshan B. Gandhi
Date of upload: January 31, 2022