S. 145(2) "Project Completion Method" vs. "Percentage Completion Method": Dept's argument that assessee should have declared profit on percentage completion method because according to AS-7, revised in 2002 with effect from 01.04.2003, the 'Completed Contract method' has been scrapped & ICAI guidelines prefer the percentage completion method is not acceptable (Realest Builders 307 ITR 202 (SC) distinguished, All judgements referred)

As regards to the adoption of project completion method of accounting by the assessee, it is seen that the assessee’s business came into existence from 11.03.2003 and since then it has been consistently following project completion method of accounting. The Ld. AR has contended that the assessee has never deviated from such method of accounting since the inception of the business and that the revenue had also accepted project completion method and profit shown by the assessee during the assessment proceedings for AY 2014-15 in assessee’s own case which also finds mention in para 6.2.1 of the order passed by Ld. CIT(A). It is well settled that the project completion method is one of the recognized method of accounting and as the assessee has consistently been followed such recognized method of accounting thus in the absence of any prohibition or restriction under the act for doing so, it can’t be held that the decision of the CIT(A) was erroneous or illegal in any manner. The judgement in the case of “CIT vs. Realest Builders & Services Ltd.”, (Supra) relied Id. DR on method of accounting is rather in favor of the assessee and against the revenue