S. 144C DRP: Action of the DRP in granting time to the assessee till 24th July 2017 to submit documents but in still passing the order on the same day itself and that too without taking on record the documents produced by the assessee is clearly unreasonable and in violation of the principles of natural justice

Clearly, the Respondent acted in violation of the principles of natural justice, since despite the time being granted to the Petitioner till 24th July 2017 to submit documents sought by the DRP, the DRP passed the order on 24th July, 2017 itself and that too without taking on record the documents produced by the Petitioner till then. The time given for the Petitioner to do so was just four days. This was clearly unreasonable, particularly, since there was an intervening weekend between 20th and 24th July, 2017

COURT:
CORAM: ,
SECTION(S):
GENRE:
CATCH WORDS: , ,
COUNSEL: ,
DATE: September 26, 2014 (Date of pronouncement)
DATE: October 4, 2014 (Date of publication)
AY: 2008-09
FILE: Click here to view full post with file download link
CITATION:
The DRP shall give clear and speaking directions to the AO for passing the assessment order and the statute ensures that the said power is not delegated to the AO.

A perusal of the above shows that the provisions of section 144C providesĀ the entire mechanism for making a reference to the DRP; the power of the DRPĀ and also the procedures which have to be followed to issue the direction to …